Development Projects

PROGRESS REPORT OF LIABILITIES SCHEMES FOR THE YEAR 2013-14

TEHSIL MUNICIPAL ADMINISTRATION CHISHTIAN UPTO 23-11-2013

(Costs In Mill

Sr. #

Name of Scheme

Name of Contractor

Estimated Cost

Agreement Cost

Exp dr

Financial Progress

Physical Progress

Remarks

ANNUAL DEVELOPMENT PROGRAMME 2009-10

 

 

 

 

 

 

 

1

Const. of soling ,Drain main road  form pacca Water Course to Chowik  Chak # 4/F.W

Munir Ahmed

0.600

0.474

0.290

61%

100%

Completed

2

Const. of sewerage  Schems Mohallah Naseer Councilor, Abdul Wahid Wali Streetr Mohajar Colony & PCC Block St. Chakki Gopi Ram Chishtian.

Munir Ahmed

0.400

0.312

0.164

52%

100%

Completed

ANNUAL DEVELOPMENT PROGRAMME 2011-12

 

 

 

 

 

 

 

1.

Construction of Metalled Road, Brick Pavement, Surface Drain, R.C.C. Sewer Pipe line Disposal Works at Chak # 9/G Tehsil Chishtian.

Aslam & Co

4.300

4.300

2.507

65%

70%

On Going

2.

P/L R.C.C Sewer & Rising Of Metalled Road Street # 4 Gulberg Town, Chishtian.

Usman Tahir

0.600

0.540

0.482

89%

100%

Completed

3.

Construction Of Metalled Road Near Court Additional Session Judge Chishtian

Usman Tahir

0.410

0.376

0.292

77%

100%

Completed

4.

Const. of Generator Room at TMA, Secretariat.

Faharib Builders

0.100

0.095

0.062

65%

100%

Completed

5.

P/L D.I. Pipe for Crossing  of Ford Wah Canal disposal  Works  satellite town Chishtian.

Faharib Builder

0.130

0.124

0.118

100%

100%

Completed

ANNUAL DEVELOPMENT PROGRAMME 2012-13

 

 

 

 

 

 

 

1.

Const. of warehouse TMA

Muhammad Bilal

0.980

0.979

0.926

95%

100%

Completed

2.

Const. of matteled road cinema road to imam bargah mehbob colony chishtian.

Sohail Bilal

1.320

1.319

1.144

87%

100%

Completed

3.

P/F manhole covers with Frames and slabs etc.U.C

Muhammad Bilal

0.350

0.349

0.322

92%

100%

Completed

DEVELOPMENT  SCHEMES 2013-14

 

 

 

 

 

 

 

1.

Providing and fixing of Man hole covers and frames, on man hole sewer line Chishtian.

Asjad Ali

1.000

0.999

-

-

25%

On Going

    

 